As expected, the construction project at Table Mesa Shopping Center moved forward this week with the Phase 1 renovation to the parking lot wrapping up with landscaping going in over the next two weeks as the weather allows.
On Monday, crews put the finishing touches on the parking lot in Phase 1 by adding striping and then they opened the lot to traffic!
Once that happened, the construction schedule moved forward and the Phase 2 area closed down for construction. This phase should last about three weeks. Phase 2 is located on the north side of Southern Sun and Under the Sun along South Broadway. Click here to see the construction phase plan.
If you are looking for parking and your favorite area is closed, please follow the “additional parking” signs. Available parking is less than a city block away from a phase of construction going on.
We are excited to see the big improvements happening at the shopping center!